GRAND MARINA, SAIGON – PROJECT UPDATE JUNE 2022

With the close construction supervision of the contractor team, the Grand Marina and Saigon construction site in June operated continuously to ensure the timely handover of the Marriott and JW Marriott branded apartment towers.

The towers of phase 1 including Cove, Lagoon, Sea and phase 2 including Strait, Spring, Bay are currently constructing the body structure of floors 3 - 4 and will be completed soon.

The Marriott-branded Lake Tower is completing the interior of the model apartment. The building is expected to come into operation in Q1/2023.

 

Picture

GRAND MARINA, SAIGON – PROJECT UPDATE JUNE 2022 GRAND MARINA, SAIGON – PROJECT UPDATE JUNE 2022 GRAND MARINA, SAIGON – PROJECT UPDATE JUNE 2022 GRAND MARINA, SAIGON – PROJECT UPDATE JUNE 2022

NEW POSTS

Cập nhật tiến độ dự án The Global City tháng 4 năm 2024

Trung tâm mới chính thức hoạt động tại The Global City – Tiến độ tháng 4/2024

Cập nhật tiến độ Grand Marina tháng 4/2024

Cập nhật tiến độ Grand Marina, Saigon tháng 4 năm 2024

Tiến độ The Global City tháng 3 năm 2024

Hoàn thiện tiến độ nhà phố SOHO bàn giao tháng 3/2024, công viên giải trí City Park đi vào hoạt động

Cập nhật tiến độ Grand Marina Saigon và Marina Central Tower tháng 2 năm 2024

Cập nhật tiến độ Grand Marina Saigon và Marina Central Tower tháng 3 năm 2024

Tiến độ The Global City tháng 2 năm 2024

The Global City: Nhà phố SOHO hoàn thiện bàn giao, công viên giải trí City Park chuẩn bị ra mắt

Tiến độ Grand Marina, Saigon tháng 1 năm 2024

Cập nhật tiến độ hoàn thiện mới nhất Grand Marina, Saigon tháng 1 năm 2024