With the close construction supervision of the contractor team, the Grand Marina and Saigon construction site in June operated continuously to ensure the timely handover of the Marriott and JW Marriott branded apartment towers.
The towers of phase 1 including Cove, Lagoon, Sea and phase 2 including Strait, Spring, Bay are currently constructing the body structure of floors 3 - 4 and will be completed soon.
The Marriott-branded Lake Tower is completing the interior of the model apartment. The building is expected to come into operation in Q1/2023.