The exterior of 5 Lumiere Boulevard buildings removed the mesh and completed 100% glazing in August 2023

By the end of July, 05 towers of LUMIÈRE Boulevard began to "show off" prominently in the middle of the big city when the net work was completed. Not only that, the work of finishing the seat includes: installing glass of balcony doors, aluminum frames and outer windows, water-based primer, 100% of all buildings have been completed.

Hoàn thành lắp kính 100% - Cập nhật tiến độ dự án Lumiere Boulevard tháng 8_2023

OUTSIDE 5 COURTS REMOVED Grating and 100% GLASS COMPLETE

By the end of July, 05 towers of LUMIÈRE Boulevard began to "show off" prominently in the middle of the big city when the net work was completed. Not only that, the work of finishing the seat includes: installing glass of balcony doors, aluminum frames and outer windows, water-based primer, 100% of all buildings have been completed.

As for the inside of the towers, two items are being synchronously constructed: (1) building bricks, waterproofing, priming, and cementing floors for raw apartments; (2) completing the interior of the corridor, making the floor, closing the ceiling, ... for apartments from floors 4 to 12.

At the same time, the landscape of the LUMIÈRE Boulevard apartment complex was also accelerated, such as the swimming pool reaching more than 90% of the construction progress and being tested for waterproofing, the planting boxes for internal utilities were also built. .

Check out the latest progress pictures of LUMIÈRE Boulevard.

The installation of balcony doors, aluminum frames and windows reached 100% of progress in 5 towers. At the same time, the work of painting the exterior (first layer) has been completed.

Hoàn thành lắp kính 100% - Cập nhật tiến độ dự án Lumiere Boulevard tháng 8_2023

The sports park of the megacity has been completed. When the LUMIÈRE Boulevard building comes into operation, residents will immediately experience this utility.

Hoàn thành lắp kính 100% - Cập nhật tiến độ dự án Lumiere Boulevard tháng 8_2023

The apartment corridor is being completed with synchronous furniture from the 4th to the 12th floor.

Hoàn thành lắp kính 100% - Cập nhật tiến độ dự án Lumiere Boulevard tháng 8_2023

The construction and finishing work inside the 5 towers is still going as planned:

– Construction of partition walls achieved 97% of the overall project progress

– Internal primer achieves 93% of the overall project progress

– Waterproof paint achieves 88% of the overall project progress

– The cement screed work reached 84% of the overall project progress

Hoàn thành lắp kính 100% - Cập nhật tiến độ dự án Lumiere Boulevard tháng 8_2023

Similarly, the apartments are also being accelerated by the Masterise Homes team and the contractor to complete the interior from the 4th to the 12th floors in 5 buildings.

Hoàn thành lắp kính 100% - Cập nhật tiến độ dự án Lumiere Boulevard tháng 8_2023
Hoàn thành lắp kính 100% - Cập nhật tiến độ dự án Lumiere Boulevard tháng 8_2023

Contact Lumiere Boulevard via:

Hotline: 0911 525 454

Address LUMIÈRE Boulevard Sales Gallery: Do Xuan Hop Street, An Phu Ward, District 2, HCMC.

Project website: https:// masterisesaigon.com/lumiere-boulevard/

NEW POSTS

Cập nhật tiến độ dự án The Global City tháng 4 năm 2024

Trung tâm mới chính thức hoạt động tại The Global City – Tiến độ tháng 4/2024

Cập nhật tiến độ Grand Marina tháng 4/2024

Cập nhật tiến độ Grand Marina, Saigon tháng 4 năm 2024

Tiến độ The Global City tháng 3 năm 2024

Hoàn thiện tiến độ nhà phố SOHO bàn giao tháng 3/2024, công viên giải trí City Park đi vào hoạt động

Cập nhật tiến độ Grand Marina Saigon và Marina Central Tower tháng 2 năm 2024

Cập nhật tiến độ Grand Marina Saigon và Marina Central Tower tháng 3 năm 2024

Tiến độ The Global City tháng 2 năm 2024

The Global City: Nhà phố SOHO hoàn thiện bàn giao, công viên giải trí City Park chuẩn bị ra mắt

Tiến độ Grand Marina, Saigon tháng 1 năm 2024

Cập nhật tiến độ hoàn thiện mới nhất Grand Marina, Saigon tháng 1 năm 2024