By the end of July, 05 towers of LUMIÈRE Boulevard began to "show off" prominently in the middle of the big city when the net work was completed. Not only that, the work of finishing the seat includes: installing glass of balcony doors, aluminum frames and outer windows, water-based primer, 100% of all buildings have been completed.
OUTSIDE 5 COURTS REMOVED Grating and 100% GLASS COMPLETE
By the end of July, 05 towers of LUMIÈRE Boulevard began to "show off" prominently in the middle of the big city when the net work was completed. Not only that, the work of finishing the seat includes: installing glass of balcony doors, aluminum frames and outer windows, water-based primer, 100% of all buildings have been completed.
As for the inside of the towers, two items are being synchronously constructed: (1) building bricks, waterproofing, priming, and cementing floors for raw apartments; (2) completing the interior of the corridor, making the floor, closing the ceiling, ... for apartments from floors 4 to 12.
At the same time, the landscape of the LUMIÈRE Boulevard apartment complex was also accelerated, such as the swimming pool reaching more than 90% of the construction progress and being tested for waterproofing, the planting boxes for internal utilities were also built. .
Check out the latest progress pictures of LUMIÈRE Boulevard.
The installation of balcony doors, aluminum frames and windows reached 100% of progress in 5 towers. At the same time, the work of painting the exterior (first layer) has been completed.
The sports park of the megacity has been completed. When the LUMIÈRE Boulevard building comes into operation, residents will immediately experience this utility.
The apartment corridor is being completed with synchronous furniture from the 4th to the 12th floor.
The construction and finishing work inside the 5 towers is still going as planned:
– Construction of partition walls achieved 97% of the overall project progress
– Internal primer achieves 93% of the overall project progress
– Waterproof paint achieves 88% of the overall project progress
– The cement screed work reached 84% of the overall project progress
Similarly, the apartments are also being accelerated by the Masterise Homes team and the contractor to complete the interior from the 4th to the 12th floors in 5 buildings.