Lumiere Riverside - Progress update as of July 2023, gradually completing the handover of apartments.

100% of the protective mesh has been removed, and the corridors are being gradually completed with 100% marble stone.

By the end of June 2023, the two existing LUMIÈRE Riverside towers stand out on the frontage of Hanoi Highway thanks to their distinctive colors and prime location in Thao Dien.

CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE

The aluminum and glass facade, which provides a sophisticated appearance, can be easily noticed enveloping the exterior of the building and commercial areas. It has been completed over 90% and is currently undergoing inspections on the upper floors.

CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE

Inside, the architectural works have been completed up to 100% on the 32nd floor of the East Tower and the 40th floor of the West Tower. The MEP system has closely followed the floor completion, and the interior fit-out (ID fitout) has also reached the 30th floor for both towers. Particularly, the tiling and granite construction works have been implemented for the corridors and interior of the apartments on multiple floors in both towers, completing up to the 19th floor for the East Tower and the 22nd floor for the West Tower.

Parallel to that, the project is installing planters for the communal area and along the two towers in accordance with the "leafscape" design. The internal roads and landscaping will progress rapidly in the near future.

Masterise Homes, along with professional partners, continues to closely monitor the construction phases according to strict standards, ensuring the completion of the LUMIÈRE riverside project with international quality. Designed in the unique green "leafscape" architectural style, LUMIÈRE riverside is an exquisite architectural masterpiece, striking a harmonious balance between nature and sophisticated luxury living. 

CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE CẬP NHẬT TIẾN ĐỘ THÁNG 7_2023 LUMIERE RIVERSIDE

Contact

Hotline: 0911 525 454

Website Masterise Homes : https://masterisesaigon.com/masterise-group/

NEW POSTS

Cập nhật tiến độ dự án The Global City tháng 4 năm 2024

Trung tâm mới chính thức hoạt động tại The Global City – Tiến độ tháng 4/2024

Cập nhật tiến độ Grand Marina tháng 4/2024

Cập nhật tiến độ Grand Marina, Saigon tháng 4 năm 2024

Tiến độ The Global City tháng 3 năm 2024

Hoàn thiện tiến độ nhà phố SOHO bàn giao tháng 3/2024, công viên giải trí City Park đi vào hoạt động

Cập nhật tiến độ Grand Marina Saigon và Marina Central Tower tháng 2 năm 2024

Cập nhật tiến độ Grand Marina Saigon và Marina Central Tower tháng 3 năm 2024

Tiến độ The Global City tháng 2 năm 2024

The Global City: Nhà phố SOHO hoàn thiện bàn giao, công viên giải trí City Park chuẩn bị ra mắt

Tiến độ Grand Marina, Saigon tháng 1 năm 2024

Cập nhật tiến độ hoàn thiện mới nhất Grand Marina, Saigon tháng 1 năm 2024